Question 1 of 25

1 A product owner at Kito Health Group in Lagos believes patients would pay NGN 1,500 a month for home delivery of repeat prescriptions. The board offers NGN 90 million for a full platform build, but no patient has yet been asked. What should the product owner do FIRST?
2 Which approach should the Scrum Master at Kito Energy SARL recommend FIRST? An agile suitability assessment for a solar-plant maintenance app in Ouarzazate scores team buy-in and trust high, but the plant's safety regulator must approve a fixed hardware design before any work starts.
3 The team at Kito Systems SARL in Casablanca has grown from five to nine people in a month. Stand-ups now start late, code reviews wait for days, and two newcomers say they do not know the team's habits. Which action is MOST appropriate for the Scrum Master?
4 Kito Systems SARL keeps the risks for its payroll product in a spreadsheet that only the delivery lead opens. Developers in Casablanca and Tangier hear about risks weeks late, and the client in Rabat is surprised at each review. What should the Scrum Master do FIRST?
5 A Scrum Master at Kito Assurance PLC in Nairobi notices that since the claims director began attending retrospectives, developers say little and describe each issue as minor. Which two actions should the Scrum Master take FIRST to restore psychological safety? Select TWO.
6 When Kito Logistics Ltd in Kano starts a route-planning app for its truck drivers, the sponsor asks the team to gather requirements from managers for three months and show drivers the finished app at launch. Which approach is MOST appropriate for the product owner?
7 The team at Kito EdTech SARL in Marrakech spent three sprints on a quiz builder for teachers. Usage data now shows that few teachers use it, while many ask for lessons that work offline in rural schools. Some developers feel their work was wasted. What is the BEST response for the product owner?
8 Which approach is MOST appropriate FIRST for the Scrum Master at Kito Systems SARL? The client now requires test-driven development (TDD) on its banking API, and none of the six developers in Casablanca has written a unit test before, though they are keen to learn.
9 A Scrum Master at Kito Logistics Ltd sees that the continuous integration build for the fleet app has failed on 9 of the last 15 working days. Each time a developer patches it quickly, and the causes seem to vary between test data, environment settings and merge timing. What should the Scrum Master do FIRST?
10 Kito Assurance PLC will lose its only actuarial-rules developer in Nairobi when she relocates in six weeks, and two Scrum teams depend on her knowledge of the premium engine. Which two actions should the Scrum Master take FIRST to spread her knowledge? Select TWO.
11 The head of delivery at Kito Retail PLC in Lagos wants to rank the company's five Scrum teams by velocity each month and reward the top team, although each team uses its own story-point scale. Which response by the Scrum Master is MOST appropriate?
12 In the kick-off week for a grid-fault reporting app at Kito Energy SARL in Rabat, engineers, call-centre staff and the finance team each describe a different purpose for the product. What should the product owner do FIRST?
13 Two developers at Kito Logistics Ltd disagree about whether the driver app should sync through a message queue or a REST API. The debate has stayed respectful and focused on facts, but it has stalled sprint planning twice. What is the best course of action for the Scrum Master?
14 Which feature should the product owner at Kito Retail PLC give the highest priority in the next Planning Interval? The Agile Release Train scored four features on business value, time criticality, risk reduction and job size: click-and-collect 8, 5, 3, size 8; loyalty points 5, 8, 2, size 3; supplier portal 13, 3, 5, size 13; fraud alerts 3, 13, 8, size 8.
15 During planning poker at Kito Assurance PLC, estimates for a story that lets customers upload accident photos range from 2 to 13 points, and the product owner suggests simply taking the average of 6. What should the Scrum Master suggest FIRST?
16 Kito Retail PLC released a one-page checkout last month with the agreed outcome of cutting cart abandonment from 68% to 55%. The epic is marked done and the team is keen to start the next one. What should the product owner do FIRST?
17 A Scrum Master at Kito EdTech SARL notices that the team finishes stories each sprint but releases to schools only once a term. Teachers complain that fixes arrive months after they report problems, and the next release is ten weeks away. What should the Scrum Master recommend FIRST?
18 After mapping the value stream for meter-fault fixes, the Scrum Master at Kito Energy SARL finds 3 days of hands-on work in an 18-day lead time. Each fix waits 6 days for a weekly change board and passes through three separate teams. Which two items should the team target first to cut waste? Select TWO.
19 The team at Kito Health Group is building an e-prescription service for pharmacies in Abuja. Pharmacists have rejected two increments in a row, saying the stories meet the written criteria but not how dispensing really works. Which two actions should the product owner take FIRST? Select TWO.
20 Which action is MOST appropriate for the agile coach at Kito Assurance PLC? The claims-support team uses Kanban with WIP limits, but managers phone developers directly with urgent requests, so half the cards in progress never appeared on the board.

Case 1: Kito FinTech Ltd merchant wallet

Kito FinTech Ltd, a mobile-money company in Nairobi, Kenya, runs a Scrum team of seven building KitoPay, a wallet that lets small merchants accept payments and pay suppliers. The team works in two-week sprints. The product owner sits with the merchant operations unit, and the sponsor follows progress on a release burndown chart.

Sprint metrics

SprintVelocity (points)Scope added (points)Escaped defects
52802
634103
731155
835207

Release status after sprint 8

  • Remaining release scope: 200 story points
  • The product owner and sponsor have agreed to freeze scope for this release
  • The sponsor wants a forecast in whole sprints

Other observations

  • Each sprint backlog is a mix of unrelated stories with no sprint goal; merchant onboarding is the company's top priority this quarter
  • Merchants report more failed payments after each release
  • A risk register lists three risks the team has never reviewed: the SMS gateway contract ends in ten weeks and the new provider is untested; the wallet has not been load-tested above 5,000 transactions a minute; and a data-protection audit is due before launch
21 The team is asked by the sponsor for a release forecast in whole sprints. Using the average velocity of the last four sprints in the case table, which forecast is MOST appropriate for the product owner to give?
22 Kito FinTech Ltd's sponsor sees on the release burndown that remaining work has barely fallen over sprints 6 to 8 and concludes that the team is slowing down. Which change to the charts should the Scrum Master make FIRST?
23 A rising trend in escaped defects, 2, 3, 5 and 7 over sprints 5 to 8, now worries the merchants of Kito FinTech Ltd. Which next step is MOST appropriate for the Scrum Master?
24 Which action should the Scrum Master at Kito FinTech Ltd take first to manage the three risks in the register, none of which the team has yet reviewed or planned for?
25 The head of merchants at Kito FinTech Ltd says she cannot tell what each sprint delivers for merchant onboarding, the top priority this quarter. Which step at the next sprint planning is MOST appropriate for the product owner?