Cost slope = (crash cost - normal cost) / (normal time - crash time), in MAD per week:
| Activity |
Weeks available |
Cost slope (MAD) |
| A |
1 |
60,000 |
| B |
2 |
40,000 |
| C |
2 |
30,000 |
| D |
1 |
25,000 |
| E |
2 |
20,000 |
| F |
1 |
50,000 |
| G |
0 |
cannot crash |
Only critical activities are crashed. E has the lowest slope but is not critical, so crashing it would not shorten the project.
- Step 1 (24 to 23 weeks): crash D, the cheapest critical activity, by 1 week at MAD 25,000. A-B-D-F-G and A-C-F-G are now both 23 weeks.
- Step 2 (23 to 22 weeks): both paths must be shortened. Options: A (60,000), F (50,000) or B + C together (70,000). Crash F by 1 week at MAD 50,000. Both paths are 22 weeks.
- Step 3 (22 to 21 weeks): F and D are exhausted. Options: A (60,000) or B + C (70,000). Crash A by 1 week at MAD 60,000. All three paths are now 21 weeks or less (A-B-E-G = 20).
Total crashing cost = 25,000 + 50,000 + 60,000 = MAD 135,000. New project cost = 4,520,000 + 135,000 = MAD 4,655,000 for 21 weeks.
Advice. Without crashing, the 3-week delay costs a penalty of 3 x 70,000 = MAD 210,000, giving a total of MAD 4,730,000. Each crashing step costs less than the MAD 70,000 weekly penalty, so crashing to 21 weeks is justified and saves MAD 75,000 (210,000 - 135,000). Youssef should note that the project then has two critical paths (A-B-D-F-G and A-C-F-G, with A-B-E-G one week short of critical at 20 weeks), so any slippage on either will now delay completion.