PRINCE2F Exam 1

PRINCE2F Exam 1

Test your knowledge with this quiz

21
Questions
25
Minutes
Click the button below to start the timer and begin your quiz
Time Remaining 00:00

Question 1 of 25

1 Amani Construction Ltd in Kumasi, Ghana, will build a district clinic by completing the design, foundations, structure and fit-out in a fixed order, handing the finished building over at the end. Which delivery approach is MOST appropriate to describe this project?
2 When starting up a store-refurbishment project, the project manager at Amani Retail PLC in Casablanca reviews the lessons reports from three earlier refurbishments and records the relevant points in the lessons log. Which principle is MOST appropriate to describe what she is doing?
3 Amani Systems Ltd in Accra is running a three-month data-migration project. The project manager proposes that one person holds both the executive and senior user roles and that highlight reports are given verbally. Which statement is MOST appropriate about applying the principles here?
4 Which term is MOST appropriate for a union at Amani Logistics Group in Tangier that believes a new warehouse shift rota will harm its members, although the project team expects no effect on them?
5 The project manager of a ward-digitisation project at Amani Council in Kisumu, Kenya, notices that nurses are resisting the new tablets, although the tablets passed every quality check. Which action is MOST appropriate to help the change succeed?
6 Amani Retail PLC is preparing the PID for a loyalty app in its Rabat and Marrakesh stores. The project manager needs to record how store staff will be prepared for, and supported through, the move to new ways of working. Which part of the PID is MOST appropriate?
7 Which item is MOST appropriate to record as a dis-benefit in Amani Logistics Group's business case for new container scanners in Tangier, given these expected results: the installed scanners, faster gate clearance, lower demurrage costs and higher electricity costs?
8 After the project board authorises initiation, the project manager of Amani Council's new school-block project in Kisumu must develop the outline business case from the project brief into a detailed business case. Which process is MOST appropriate for this work?
9 Amani Construction Ltd is the main contractor building a market hall for a municipal council in Tamale, Ghana. The council's executive needs to decide who should sit on the project board for those designing and building the hall. Which role is MOST appropriate?
10 The executive of Amani Systems Ltd in Accra wants someone independent of the project manager to check, on the board's behalf, that the project is being run properly and that stakeholder needs are being met. Which role is MOST appropriate?
11 Amani Retail PLC's project manager for a warehouse-racking project in Casablanca has just written the project product description. Which planning step is MOST appropriate to complete next?
12 During a quality review of the user guide for Amani Council's tender portal in Kisumu, the reviewers agree that the guide meets its quality criteria. Which record is MOST appropriate for the project manager to update with this result?
13 Following a workshop, the senior user of Amani Logistics Group says the new tracking system must be 'fast and reliable'. The project manager turns this into measurable statements such as 'pages load in under 2 seconds' and '99.5% availability'. Which quality concept is MOST appropriate for these statements?
14 Amani Construction Ltd's project manager in Kumasi writes: 'Because heavy rain is forecast for May, the foundation trenches may flood, which could delay the structural work by three weeks.' Which part of this statement is MOST appropriate to describe as the risk event?
15 After acceptance testing, the team manager at Amani Systems Ltd reports that the new payroll module cannot produce the monthly tax schedule that its product description requires. Which issue type is MOST appropriate to record?
16 Which report is MOST appropriate for the project manager of Amani Retail PLC's store-rollout project to use when giving the project board a regular, time-driven summary of stage progress?
17 Following board approval at the end of initiation, Amani Logistics Group's project manager is asked which management product will act as the baseline for managing the project and assessing its progress. Which product is MOST appropriate?
18 Amani Council in Kisumu has received a project mandate for a new county revenue-collection system. Before committing resources to initiation, the executive wants to confirm that the project is viable and worthwhile. Which process is MOST appropriate?
19 A team manager at Amani Construction Ltd has accepted a work package to build the drainage works for a clinic in Kumasi. Which process is MOST appropriate for controlling the link between the project manager and the team manager during this work?
20 As the final stage nears completion, the executive of Amani Systems Ltd asks which process will confirm that users have accepted the products and that the host site can support them once the project team disbands. Which process is MOST appropriate?

Case 1: Amani Health Group maternity wing (Nairobi)

Amani Health Group is building a 60-bed maternity wing at its hospital in Nairobi, Kenya, using a linear-sequential approach. The group's chief operating officer is the executive; the head of maternity services is the senior user; the director of the building contractor is the senior supplier. Wanjiru Kamau is the project manager. The project board has made the hospital facilities director the change authority, able to approve requests for change of up to KES 5 million each from a change budget of KES 10 million.

Key facts in month 7:

  • Stages: 1 initiation (complete); 2 design and approvals (complete); 3 construction (in progress, months 4 to 12); 4 fit-out and commissioning.
  • Stage 3 budget: KES 480 million, with a cost tolerance of plus or minus KES 24 million and a time tolerance of plus or minus three weeks.
  • Only stage 3 has a detailed stage plan; stage 4 is shown at outline level in the project plan.
  • A steel supplier has warned that prices may rise by 12% next quarter.
  • The senior user has asked for a second neonatal theatre, estimated at KES 18 million.
  • Because of higher cement and steel prices already incurred, Wanjiru now forecasts that stage 3 will finish KES 31 million over budget.
21 Which timing is MOST appropriate for Amani Health Group to produce the detailed stage plan for stage 4, the fit-out and commissioning work?
22 The project manager has asked the hospital's procurement manager to take responsibility for the steel-price risk and has asked a buyer to place a fixed-price forward order for steel. Which role does the buyer MOST appropriately hold for this risk?
23 When Wanjiru logs the senior user's KES 18 million request for a second neonatal theatre at Amani Health Group as a request for change, which handling is MOST appropriate?
24 Wanjiru Kamau now forecasts that stage 3 at Amani Health Group will finish KES 31 million over its KES 480 million budget. Which action should she take FIRST?
25 After receiving Wanjiru's exception report, Amani Health Group's project board must decide whether to ask for an exception plan for stage 3. Which process and management level is MOST appropriate for this decision?