Question 1 of 25

1 Mwangaza Paints Ltd runs its Nairobi tin-filling line on two 480-minute shifts a day. Each shift has a 30-minute lunch and two 10-minute tea breaks. Daily demand is 1,200 tins. Which takt time is most appropriate for balancing the line?
2 A process FMEA for the crimping cell at Tangier Harness Works Ltd rates four failure modes (severity, occurrence, detection): crimp height low 7, 6, 5; wire colours swapped 8, 3, 7; terminal not seated 9, 4, 4; seal missing 6, 5, 8. Which failure mode is the most appropriate to action first on risk priority number?
3 Which candidate project is most appropriate for Sokoto Grain Mills PLC to charter first, given that its strategic goal this year is to halve bakery complaints about caked flour, and complaint data show moisture variation in 50 kg bags drives 62% of them?
4 Three activities on the critical path of a warehouse-system project at Umgeni Freight (Pty) Ltd in Durban have estimates (optimistic, most likely, pessimistic) of 4, 6, 14 days; 6, 9, 18 days; and 2, 3, 4 days. Which PERT expected duration for the path is most appropriate for the schedule?
5 After inspecting 2,400 plastic crates at Ikeja Polymers PLC in Lagos against 6 defect opportunities per crate, a Green Belt records 216 defects. Which DPMO and sigma level, using the 1.5 sigma shift, are most appropriate to report?
6 A Casablanca sardine-canning company is translating retailer complaints that its cans are 'hard to open' into a CTQ tree for a Green Belt project. Which critical-to-quality requirement is most appropriate at the lowest level of the tree?
7 In the Durban depot of Umgeni Freight (Pty) Ltd, a Green Belt records fuel use for the same 15 trucks for a month before and a month after an eco-driving course. Which test is most appropriate to decide whether the course reduced fuel use?
8 A Johannesburg packaging company has formed a project team that agrees within minutes to the sponsor's preferred solution, and no member raises concerns or offers another idea. Which action by the Green Belt is most appropriate?
9 Which predicted shrinkage is most appropriate for Ikeja Polymers PLC at a mould temperature of 235 °C, after a Green Belt fits a least-squares line to five trials at 200, 210, 220, 230 and 240 °C that gave shrinkage of 2.6, 2.3, 2.0, 1.6 and 1.4%?
10 A Meknes olive-oil company collects six consecutive 1-litre bottles from its filler, with fills of 1,002, 998, 1,001, 1,004, 997 and 1,000 mL. Which sample standard deviation is the most appropriate estimate of fill variation?
11 When a 5 Whys session at Mwangaza Paints Ltd on wrongly tinted 20-litre tins stops at 'the operator selected the wrong base', the team proposes retraining. Which response by the Green Belt is most appropriate?
12 A Cape Town wine-bottling company wants to estimate the proportion of mislabelled cases within ±2 percentage points at 95% confidence. A pilot audit found 6% mislabelled. Which sample size is most appropriate for the data collection plan?
13 Sokoto Grain Mills PLC plans a 2² experiment on conditioning time and added water to cut flour caking, but one wheat lot can supply only half of the eight runs, so two lots are needed. Which design choice is most appropriate?
14 A Kano tomato-paste manufacturer has compared seal strength for 400 cans from each of two lid suppliers. Mean strength is 45.0 N versus 45.2 N, the two-sample t-test gives p = 0.01 at α = 0.05, and the specification is at least 30 N. Which conclusion is most appropriate?
15 Within the crimping cell at Tangier Harness Works Ltd, a 48-minute changeover includes 30 minutes in which the press stands idle while the operator fetches the next applicator and finds gauges. Which first SMED step is most appropriate?
16 Operators at Ikeja Polymers PLC occasionally load the wrong mould insert, producing crates with the wrong customer logo that are found only at dispatch. Which mistake-proofing action is most appropriate?
17 Which next step is most appropriate for the project team at Umgeni Freight (Pty) Ltd at its Improve toll gate, now that a new cross-dock scheduling method has worked in a simulation and the sponsor wants it running at six depots?
18 Audits of 20-harness lots at Tangier Harness Works Ltd found 400 defects across 25 lots, with the lot size held constant. Which control limits are most appropriate for the c chart of defects per lot?
19 Once the project at Mwangaza Paints Ltd is ready for handover, its draft control plan lists each CTQ, its specification, the measurement method, and the sample size and frequency. Which element is most appropriate to add before the process owner signs off?
20 Unplanned stoppages of the roller mills at Sokoto Grain Mills PLC trace mainly to bearing failures that give rising vibration for several days beforehand. Which total productive maintenance approach is most appropriate?

Case 1: Naivasha Bloom Growers Ltd — packhouse stem-length capability study

The case is hidden so you can see the question. Select Show case to read it again.

Naivasha Bloom Growers Ltd grows roses near Lake Naivasha and grades them in its packhouse for export auctions. The 60 cm grade must have a cut stem length between 56.0 cm and 64.0 cm. After a buyer rejected two consignments, a Green Belt supported by a Black Belt starts the Measure phase of a DMAIC project with the packhouse manager as process owner.

Measure-phase data (cut-stem length, cm)

ItemValue
Measuring board gauge R&R studyσGRR = 0.10 cm
Sampling25 subgroups of 4 consecutive stems, one subgroup per 30 minutes
Grand mean (X-double-bar)60.8 cm
Average range (R-bar)2.06 cm
Constant for n = 4d2 = 2.059
Overall standard deviation of all 100 stems1.25 cm
Normality checknormal probability plot close to a straight line; Anderson–Darling p = 0.38

On the first X-bar chart no point falls outside the control limits, but subgroups 14 to 21 all sit above the centre line. Those eight subgroups were cut on the night shift after a new blade guide was fitted. The guide was reset and fresh data were collected, which gave the summary above. The buyer's contract requires a long-term performance index of at least 1.33.

21 Which precision-to-tolerance ratio and conclusion are most appropriate for the measuring board at Naivasha Bloom Growers Ltd, based on the gauge R&R result and the 56.0–64.0 cm specification?
22 The first X-bar chart at Naivasha Bloom Growers Ltd showed eight subgroups in a row above the centre line after the new blade guide was fitted. Which action was most appropriate before any capability index was reported?
23 Under the study plan at Naivasha Bloom Growers Ltd, the team checked whether stem length follows a normal distribution before using normal-based indices. Which conclusion from the plot and the Anderson–Darling p-value is most appropriate?
24 Once the reset blade guide gave stable data, the Black Belt asked for short-term capability at Naivasha Bloom Growers Ltd using the R-bar estimate of sigma. Which Cp and Cpk are most appropriate to report?
25 The export buyer's contract with Naivasha Bloom Growers Ltd sets a long-term performance target of 1.33. Which Pp, Ppk and conclusion are most appropriate for the Green Belt to report to the champion?